HomeMy WebLinkAbout2005-11,~
TOWN OF PULASHI
• RESOLUTION 2005-11
REGARDING REVISIONS TO CEMETERY LOT PRICES
WHEREAS, the Town of Pulaski is responsible for the care of municipal cemeteries,
including maintenance and the sale of lots including those in Oakwood and Pinehurst;
and
WHEREAS, lot sale income is distributed 25% to maintenance and 75% to build up to a
perpetual care fund; and
WHEREAS, the Town Council desires to increase funds available for maintenance and
to accelerate the accumulation of funds for eventual perpetual care; and
WHEREAS, the Town of Pulaski lot sale prices are generally low in comparison to
certain other public and private cemeteries; and
WHEREAS, the Cemetery Trustees have recommended that lot prices that presently
range from $150 to $300 at Oakwood and Oakwood Addition, respectively; and $75 to
$225 at Pinehurst and Pinehurst Addition, respectively, be increased proportionately by
$50 at each location.
NOW, THEREFORE, be it RESOLVED by the Town Council of the Town of Pulaski,
Virginia that the proposed price revisions be approved and be as follows: $200 and $350
at Oakwood and Oakwood Addition, respectively; and $125 and $275 at Pinehurst and
Pinehurst Addition, respectively, effective beginning April 1, 2005.
This Resolution is effective upon adoption and is hereby adopted this 15th day of March,
2005, by recorded vote of the Town Council of the Town of Pulaski, Virginia as follows:
Jeffrey S. Worrell -Aye Lane R. Penn -Aye
Dan Talbert, Jr. -Aye John T. Bolen -Aye
Bettye H. Steger -Aye Joel B. Burchett, Jr. -Aye
Town of Pulaski, Virginia
By:
Charles L. a e, Mayor
ATTESTED:
c'
Patricia Cruise, Clerk of Council
• Attachment "A"
Change 1-Placement of Oversize Rock
Provisions will be made to allow for Oversize rock placement in designated areas. In the areas designated
by the Soils Engineer, the maximum rock size shall be 18" diameter when placed in a 24" lift of rock fill at
the direction and observation of the Soils Engineer.
Summary of cost change = ($ 250,000)
Change 2 -Additive Bid Item 2 - Ezcavation of Additional Unsuitable Material
H.T. Bowling shall revised their unit price to $4 / CY for this work.
Change 3 -Responsibility for the First Three Feet of Undercut
Summary of cost change ~ (S 12,000)
The Contractor shall be paid for the first three feet of undercut, beneath fill or cut, at a unit price of $4.00
per cubic yard.
Summary of cost change a ($ 400,000)
Change 4 -Eliminate Additive Bid Item 5 -lime 1Yeatment
The estimated quantity for the Lime Treatment shall be reduced to zero (0) tons.
Summary of cost change = ($1,000,000)
Change S -Additive Bid Item # 4 - Importing of Ofl'-Site Fill Material
The estimated quantity for Additive Bid Item # 4 shall be revised to be 150,000 / CY. The Town of Pulaski
• has agreed to provide aflag--man at the borrow site. Additionally, H.T. Bowling's unit price shall be
revised to be $10 / CY.
Summary of cost changes $900,000
Change 6 -Installation of Erosion Control for Waste Areas
The Town of Pulaski shall be responsible for the implementation of the erosion control measures as needed
for the wasting of the unused, excavated material in a designated area on the property owned / controlled by
the Town a~f Pulaski
Change 7 -Additive Bid Item #3 -Additional Rock Ezcavation
Summary of cost change = ($ 50,000)
The estimated quantity for this bid item shall be revised to be 5,000 CY.
Summary of cost change = $ 9(1,000
GRAND TOTAL = $ 5942.450.00
•